T&M ticket: what to record and get signed every day
Fiveover editorial team 8 min read
Time-and-materials work is where many job disputes start. The work gets done, the crew moves on, and three weeks later an invoice arrives for hours nobody remembers approving. The fix is boring and it works: a ticket for each day, written on site, signed by the customer’s rep before you leave.
This guide is for tradespeople and small contractors. It covers what a T&M ticket (or daily report) should record, who signs it and when, how it fits with change orders, and what California requires for home improvement work. Other states have their own rules, and your contract comes first.
What a T&M ticket is
On a time-and-materials job, or a T&M portion of a fixed-price job, you are paid for the labor hours and materials actually used, at agreed rates, plus any agreed markup. The ticket is the daily record of those hours and materials. Many contractors fill in a daily report on every job and a T&M ticket only for extra work, and some use one form for both.
The ticket isn’t the bill. It is what the bill is built from, and the document the customer looks at when the bill arrives.
What it records
| Field | What to write |
|---|---|
| Job | Project name and address, job or PO number, contract or change order reference |
| Date | The day the work was done, one ticket per day |
| Directed by | Who asked for the work, when, and how (in person, phone, email) |
| Work done | What was done and where, in plain sentences: “Removed and replaced 12 sq ft of rotted subfloor under the tub” |
| Labor | Each worker by name and trade or classification, start and end time, hours, rate if agreed |
| Materials | Each item with quantity and unit, and the price or “per invoice” |
| Equipment | Each piece, hours or days used, and rate |
| Delays and notes | Waiting for access, inspections, another trade in the way, conditions found |
| Photos | Before, during and after, especially anything that will be covered up |
| Next steps | What’s left, what you need from the customer |
| Signature | Customer’s rep: printed name, title, date and time, and any remark |
Two habits make tickets far easier to approve. Write the work so someone who wasn’t there understands it. And photograph anything that disappears behind drywall, under flooring or into the ground, because by the time the invoice comes, nobody can look.
Federal contracts show how much weight these records carry. On federal time-and-materials and labor-hour contracts, the payments clause (FAR 52.232-7) asks contractors to back up their invoices with records including individual daily job timekeeping records. Private contracts rarely spell it out that formally, but the same records are what a customer will ask to see.
Get it signed every day
A ticket signed the same day by someone who watched the work is much harder to dispute later. A batch of tickets presented at the end of the month is easy to argue with. Memories fade, the superintendent who asked for the work moves to another job, and the owner’s accountant sees only a number.
Practical rules:
- Agree at the start who signs. The owner, the general contractor’s superintendent, the owner’s project manager. Get the name in writing, ideally in the contract or the change order.
- Sign before you leave. At the end of the day, walk the rep through the ticket, let them add a remark if they disagree with something, and get the signature.
- Send a copy the same day. Email it to the rep and to whoever approves payment.
- If they won’t sign, write “presented to [name] at 4:30 p.m., not signed” on the ticket, send it the same day, and ask for corrections in writing. Then check the contract for how disputed extra work is handled and for any notice deadlines.
- Don’t let tickets pile up. One unsigned day is a conversation. Ten are a dispute.
A signature usually confirms that the hours and materials were on site, not that the customer agrees to pay for them as extra. Whether it’s extra is decided by the contract and the change order.
T&M tickets and change orders
These are two different documents, and mixing them up is a common source of T&M disputes.
- A change order changes the contract: what will be done, what it costs, and how the payments change. It is agreed before the work.
- A T&M ticket records what was done on a given day. It is written during or after the work.
When extra work is priced as T&M, you usually need both: a change order that says the work will be done on a T&M basis, often with a not-to-exceed amount, and daily tickets that show the hours and materials against it.
California: change orders on home improvement contracts
For home improvement contracts in California, Business and Professions Code § 7159 sets what the contract must contain. It generally applies to home improvement contracts with a price over $500. Among its rules:
- A change order for changes or extra work becomes part of the contract only if it is in writing and signed by the parties before the work it covers begins.
- It describes the scope of the extra work or change, the cost added or subtracted, and the effect on the schedule of progress payments.
- Changes required by the building department at the jobsite are an exception to the signing requirement.
The Contractors State License Board tells homeowners the same: when the price or the scope changes, it must be done with a written change order signed by the customer and the contractor before the change, and a contractor can’t be required to do extra work without written authorization first. The CSLB’s page on home improvement contracts covers what else the contract must include.
So on a California home improvement job, a T&M ticket signed after the fact doesn’t replace the change order signed before. Get the change order first, even a short one, then ticket the work daily.
Texas: retainage on T&M work
In Texas, start with your contract’s changes clause for how extra work is ordered and priced. One statute matters on any lien-eligible job, including T&M work: during the work and for 30 days after completion, the owner must retain 10% of the contract price, or of the value of the work done. With no contract price, the reasonable value of the completed work is used (Property Code § 53.101). On a T&M job, signed daily tickets are what both sides use to know that value.
Other states have their own home improvement, change order and retainage rules. Check yours, and read your contract’s changes clause before the first extra hour.
Worked example
A plumbing contractor is on a bathroom remodel in San Diego under a home improvement contract. On Tuesday, October 6, 2026, the crew pulls the old tub and finds the subfloor rotted under it. At 10:15 a.m. the homeowner and the contractor sign change order CO-04: replace the damaged subfloor on a T&M basis at the contract rates, not to exceed $2,000, payment added to the final progress payment.
The ticket for October 6:
| Item | Quantity | Rate | Amount |
|---|---|---|---|
| Journeyman plumber, 7:30 to 4:00, 1 h lunch | 7.5 h | $110/h | $825.00 |
| Apprentice, 9:30 to 4:00, 30 min lunch | 6 h | $70/h | $420.00 |
| Plywood, 3/4 in, 4 × 8 ft | 2 sheets | $62.00 | $124.00 |
| Subfloor screws | 1 box | $18.00 | $18.00 |
| P-trap kit | 1 | $24.00 | $24.00 |
| Markup on materials per contract | 15% | $24.90 | |
| Total for the day | $1,435.90 |
Work done: “Removed rotted subfloor under tub, about 12 sq ft, down to the joists. Sistered one joist (photos 3–6). Installed new 3/4 in plywood, screwed and glued. Replaced the P-trap, which was corroded.” Delays: “Waited 45 minutes for the homeowner to move a vanity out of the hallway.” Next steps: “Set the new tub tomorrow.” The homeowner signs at 4:10 p.m. with the remark “OK, but I want to see the joist before it’s covered”, and the contractor emails the ticket and photos at 4:30 p.m. When the invoice arrives, the line for CO-04 matches a signed ticket, with photos of a joist nobody can see anymore.
Write it before you leave
The end of a long day is when tickets get skipped. A daily report and T&M ticket lets you say what was done, who worked for how long, what materials went in and what held you up. AI writes each section, puts the hours in their field and each photo in its section, and lists what’s missing before you finish, like hours nobody mentioned. You can change anything it wrote. The owner or their rep can sign on your phone, from a QR code on theirs, or later by email, and add one remark. You get a sealed PDF with a verification code to attach to your invoice.
At the end of the job, the same approach works for the final walkthrough and punch list.
Checklist: what to write down
- Job name, address, job or PO number, and the change order it falls under
- Date, and who directed the work, when and how
- Work done, in plain sentences, with locations
- Each worker: name, trade, start and end time, hours
- Materials: item, quantity, unit, price or “per invoice”
- Equipment: item, hours or days, rate
- Delays, conditions found, who or what held you up
- Photos, especially of work that will be covered
- Next steps and what you need from the customer
- Customer rep’s printed name, signature, date and time, and any remark
- When and to whom you sent the copy
Limits and when to get advice
A T&M ticket records what happened. It doesn’t change the contract, and a signature on it doesn’t by itself make work billable as extra. Your contract’s changes clause, notice deadlines and payment terms decide that, and so do state laws on home improvement contracts, retainage and liens. If a customer disputes a run of tickets, refuses to sign change orders, or holds back payment, talk to a construction lawyer early, before lien and notice deadlines pass.
Questions people ask
- What is a T&M ticket?
- A daily record of time-and-materials work: the date and job, who worked and how many hours, what they did, the materials and equipment used, and who directed the work. The customer’s representative signs it, usually at the end of each day, and it becomes the backup for the invoice.
- Is a signed T&M ticket the same as a change order?
- No. A change order changes the contract: the scope, the price and the effect on the payment schedule. A T&M ticket records what was actually done on a day. In California, home improvement change orders must be in writing and signed before the work starts (Bus. & Prof. Code § 7159), so a signed ticket afterward is not a substitute.
- What if the customer’s rep won’t sign the T&M ticket?
- Write on the ticket that it was presented, to whom and when, and that it was not signed. Send a copy the same day by email and ask for any corrections in writing. Then check what your contract says about disputed extra work and notice deadlines, and raise it with the person who signs change orders.
- Who should sign the T&M ticket?
- Someone the contract or the customer has authorized to approve extra work, like the owner, the general contractor’s superintendent or the owner’s project manager. Ask at the start of the job who that is, and get it in writing. A signature from someone without authority may not help much.
You talk. AI writes the report.
Daily report and T&M ticket: walk through and say what you see. Then the PDF is sealed.
Sources
- Cal. Business and Professions Code § 7159 (California Legislative Information)
- Home Improvement Contracts consumer guide (Contractors State License Board)
- Learn About Home Improvement Contracts (Contractors State License Board)
- FAR 52.232-7, Payments under Time-and-Materials and Labor-Hour Contracts (Acquisition.gov)
- Texas Property Code § 53.101, required retainage (FindLaw)
General information, not legal advice. Laws change: check the linked sources for your case.