May we count which pages you open and which steps you take, such as starting a report? We use PostHog, on servers in Frankfurt, with no cookies and no profile of you. Nothing is counted unless you allow it. You can change your choice any time under “Privacy settings” at the bottom of every page. Privacy policy

We count page views and steps only if you allow it: no cookies, and no profile of you. Privacy policy

This choice applies to fiveover.app in this browser.

Skip to content
fiveover

Snagging a new build: the list and the deadlines

Fiveover editorial team 8 min read

A snag is anything in a new home that is unfinished, damaged or not built the way it should be: a chipped worktop, a door that won’t latch, a radiator that stays cold, sealant missing round the bath. Every new build has some. What decides whether they get fixed is a clear list, sent to the right people, at the right time.

This guide is written for new-build homes in England. The New Homes Quality Code and the warranty schemes also operate elsewhere in the UK, but the law differs in Scotland and Northern Ireland, and the Defective Premises Act covers England and Wales only.

When to snag: before completion and after you move in

There are two moments, and you should use both.

Before legal completion. If your developer is registered with the New Homes Quality Board (check the register of developers), the New Homes Quality Code gives you the right to a pre-completion inspection before you complete. Under the first version of the Code that inspection was done by a suitably qualified inspector you appoint. The second version, which applies to homes reserved on or after 2 March 2026, also lets you carry out the inspection yourself, as Brodies’ summary of the changes explains. The details sit in Part 2 of the Code. Before completion you still have the developer’s attention and the money has not all changed hands, so this is when obvious faults are easiest to get fixed.

After you move in. Some snags only appear once the home is lived in: the boiler cycling on and off, a shower tray that rocks, a drain that gurgles, hairline cracks as plaster dries. Keep a running list from the first day and send it in batches rather than one email per snag. Some builders’ sales terms also ask you to report cosmetic damage, such as chips and scratches, within a short period after completion, so check your handover pack for a deadline.

The two-year builder warranty period

Most new homes come with a ten-year warranty. NHBC’s Buildmark is the best known, and LABC Warranty and Premier Guarantee are among the others. Their terms are similar but not identical, so read the policy you were given.

Under NHBC Buildmark, the first two years after completion are the builder warranty period: the builder is responsible for putting right defects. If you have reported a defect and the builder does not deal with it, NHBC offers a resolution service, explained on its make a claim page. From year three to year ten, the cover is an insurance policy for defined, mainly structural, problems. Small non-structural snags that you never reported in the first two years tend to become your problem after that.

So the practical rule is simple: report every snag, in writing, inside the first two years, and keep the email.

The New Homes Quality Code and the New Homes Ombudsman

If your developer is registered, Part 3 of the Code sets the after-sales rules:

  • In most cases the developer must settle an after-sales issue within 30 days. If there is a significant reason for delay, it must explain the reason and update you at least once a month.
  • You have two years from reservation or completion, whichever is later, to raise a complaint under the developer’s complaints procedure.
  • If the complaint is not closed, the developer sends an eight-week letter no later than 56 days from the complaint start date. After 56 days, or once you have a final closure letter, you can take it to the New Homes Ombudsman Service.

Which version of the Code applies depends on when you reserved, not when you complete: homes reserved on or after 2 March 2026 fall under the second version. The Ombudsman’s remit is set out in the Code, and problems that belong to the structural warranty go to the warranty provider instead, so check which route fits before you complain.

Beyond the warranty: the Defective Premises Act

Separately from any warranty, section 1 of the Defective Premises Act 1972 says that anyone who takes on work for or in connection with the provision of a dwelling must do it in a workmanlike or professional manner, with proper materials, so that the dwelling is fit for habitation when completed. The duty is owed to the person who ordered the work and to everyone who later acquires an interest in the home, so a second owner can rely on it too.

Section 135 of the Building Safety Act 2022 made the time limit far longer. For claims where the right of action arose on or after 28 June 2022, it is 15 years. For claims that arose before that date, it is 30 years. That does not make every snag a legal claim: the duty is about work that leaves a home unfit for habitation, not a scuffed skirting board. But it matters for serious defects found after the warranty’s builder period.

How to write a snag the builder can act on

An aftercare team works from your list, often with a different person on site from the one who read it. Write each snag so a stranger could find it and fix it without ringing you.

Each snag needs:

  1. Room and level. “First floor, bedroom 2 (front)”, not “upstairs”.
  2. Exact location. Wall, height, distance from a fixed point: “window wall, 40 cm left of the window, 1.2 m up”.
  3. What is wrong. Describe it, don’t diagnose it: “hairline crack, about 30 cm, running diagonally from the window corner”, not “subsidence”.
  4. A photo, numbered. One wide shot to show where, one close-up to show what. Put a coin or tape measure in the close-up for scale.
  5. How it affects use. “Door won’t latch, so it can’t be closed” gets a different priority from “small paint run”.
  6. Date found. The date you first noticed it, especially for things that appear later.

A weak snag: “Kitchen – worktop damaged.” A good one: “Kitchen, worktop to the right of the hob: chip in the front edge, about 8 mm, laminate exposed. Photos 12–13. Found at pre-completion inspection, 9 November 2026.”

Checklist: what to write down at a snagging walk round

  • The address, plot number and the date and time of the inspection
  • Who was there, including anyone from the developer
  • Meter readings and serial numbers, with a photo of each meter
  • Keys, fobs and remote controls handed over, and how many
  • Every room in the same order, ceiling to floor
  • Doors and windows: do they open, close, lock and seal?
  • Taps, showers, toilets and drains: run water in each and check for leaks
  • Heating and hot water: does every radiator warm up?
  • Electrics: try every socket and switch, and note any that don’t work
  • Outside: brickwork, pointing, gutters, downpipes, paths, fences and drainage
  • Each snag numbered, with its photos and the date found

A worked example

You reserve a home on 10 March 2026, so the second version of the Code applies. You do the pre-completion inspection yourself on 9 November and list 23 snags. Legal completion is on 14 November.

On 16 November you send the developer’s aftercare team a numbered list with photos, including the eight snags still open from the inspection. Under the Code you would normally expect them settled by about 16 December, or an explanation and monthly updates if there is a good reason for delay.

Three snags are still open in early January, so you raise a formal complaint on 4 January 2027. If it is not resolved, 56 days from that date is 1 March 2027, after which you can refer it to the New Homes Ombudsman Service. Separately, the builder’s two-year warranty period runs to 14 November 2028. Anything new you find before then goes on the list and gets reported.

Sending the list and following up

Send the list by email to the address the developer gave you for aftercare, and keep a copy. Ask for a reference number and a date for the visit. When someone comes to fix things, update your list the same day: which snags are closed, which are still open, and what was said. A list that shows the history, snag by snag, is far easier to escalate than a memory of phone calls.

If the developer isn’t registered with the NHQB, its complaints route and any other consumer code it signed up to apply instead, and the warranty provider’s resolution service is the next step.

Snagging after building or renovation work

Snagging is not only for new builds. On a renovation, an extension or a new kitchen, the same walk round happens at practical completion: the point at which the work is finished apart from minor items and you can use it.

What happens next depends on your contract. Larger building contracts often include a defects or rectification period, commonly six or twelve months from practical completion, during which the builder must come back and fix defects that appear. A retention, a percentage of the price held back, is often released in two halves: one at practical completion and the rest at the end of that period. Many small domestic jobs have no written retention at all, so agree it before the work starts, not at the end.

When a trader supplies a service to a consumer, the Consumer Rights Act 2015 treats the contract as including a term that the work is done with reasonable care and skill.

How Fiveover helps

Our snagging list is built for the walk round itself. You walk round and talk, and AI writes each snag into the list as you go. Photos land in their section next to the snag they show, and before you finish AI lists what’s missing, such as a snag with no location. You can change anything until you finish. The person on the other side, such as the site manager or your client, can sign on your phone if they want to, and you get one sealed PDF with a verification code to send.

Limits: when to get advice

This guide explains the rules. It is not legal advice. Your sale contract, your warranty policy and the version of the Code that applies all add details this page can’t cover. If a defect is serious, structural, or affects safety, or if the developer disputes that it is a defect at all, a chartered surveyor’s report and advice from a solicitor are worth the cost before you go further. Claims under the Defective Premises Act in particular are court claims, with rules on evidence and time limits that a professional should check.

Questions people ask

Should I snag before completion or after I move in?
Both. The pre-completion inspection is your chance to get obvious faults fixed before you pay the balance. Other faults only show once you live there: heating that won’t balance, a door that sticks as the house dries out. The builder’s two-year warranty period covers both, so keep one running list from the first walk round onwards.
How long does the builder have to fix snags?
Under the New Homes Quality Code, a registered developer must usually settle an after-sales issue within 30 days and, if there is a good reason for delay, explain it and update you at least monthly. Your warranty and sale contract may say more, so read both.
When can I go to the New Homes Ombudsman Service?
If your developer is registered with the New Homes Quality Board, once you have its final closure letter or 56 days have passed since your complaint started. The complaint has to be about something within two years of reservation or completion, whichever is later.
What if a defect appears after the two years?
From year three the warranty usually covers only the defined structural parts. Separately, the Defective Premises Act 1972 lets you claim for work that left the home unfit for habitation, and for homes completed since 28 June 2022 the time limit is 15 years. That is a legal claim, so get advice first.

You talk. AI writes the report.

Snagging list: walk round and say what you see. Then the PDF is sealed.

Sources

  1. The Code (New Homes Quality Board)
  2. New Homes Quality Code, Version 2, March 2026 (NHQB)
  3. Part 2: Legal documents, information, inspection and completion (NHQB)
  4. Part 3: After-sales service, complaints and the New Homes Ombudsman (NHQB)
  5. Register of Developers (NHQB)
  6. New Homes Quality Code Version 2: the key changes for housebuilders (Brodies)
  7. About us (New Homes Ombudsman Service)
  8. NHBC warranty benefit (NHBC)
  9. Make a claim (NHBC)
  10. Defective Premises Act 1972, section 1 (legislation.gov.uk)
  11. Building Safety Act 2022, section 135 (legislation.gov.uk)
  12. Consumer Rights Act 2015, section 49: explanatory notes (legislation.gov.uk)
  13. Defects liability period (Designing Buildings)

General information, not legal advice. Laws change: check the linked sources for your case.