Acceptance of work in Germany explained
Fiveover editorial team 7 min read
In Germany, the most important moment in any job you pay a contractor for, from a new bathroom to a whole house, is not the day work starts or the day you pay. It is acceptance: the moment you confirm that the work is done essentially as agreed. In German it is called the Abnahme, and the contractor will ask for it in those words.
Many people who move here don’t know how much hangs on it. Acceptance changes who pays, who has to prove what, and how long you can complain. This guide explains the rules in the German Civil Code (BGB) for an ordinary work contract and a building contract. Contracts that include the construction industry’s standard terms (VOB/B) have their own acceptance rules on top, so check your contract.
What acceptance is
Under § 640(1) BGB, you are obliged to accept work that has been produced in line with the contract, unless the nature of the work rules acceptance out. You can’t refuse acceptance because of an insignificant defect. The Federal Ministry of Justice’s English translation of the BGB has the full wording.
Acceptance means approving the work as essentially in line with the contract. It doesn’t need a ceremony or a particular form: what you say or do can be enough. That is why a friendly “handover” with keys and a coffee can be an acceptance, whether or not anyone uses the word. If you want to reserve defects, the handover is the moment to do it, in writing.
Until acceptance, the contractor is still performing the contract, and as a rule you can’t yet make the claims for defects listed in the BGB (Deutsches Handwerksblatt). After acceptance, those claims are what you have.
What changes when you accept
1. The price becomes due
Under § 641(1) BGB, the price is due on acceptance. If the work is accepted in parts with a price for each part, each part is due on its acceptance. From acceptance, a price fixed in money also bears interest unless payment has been deferred (§ 641(4)). For building contracts, § 650g(4) BGB adds that the contractor must also have given you a final invoice you can check.
If you are entitled to have a defect fixed, you can refuse to pay an appropriate part of the price after it becomes due. That is usually twice the cost of fixing the defect (§ 641(3)).
2. You now have to prove the defect
Before acceptance, the contractor has to show the work is free of defects. After acceptance, it is the other way round: for defects you raise after acceptance, you have to show that the defect exists and that it was already there at acceptance (BG BAU). Whether something is a defect is judged as of the date of acceptance.
That is the practical reason to record the condition of the work in detail on the day, with photos.
3. The warranty clock starts
Under § 634a BGB, claims for defects become time-barred:
- after five years for a building, and for planning or supervision work on a building,
- after two years for making, servicing or altering a thing, such as repairing a car or a bike,
- otherwise after the general limitation period.
The two-year and five-year periods start with acceptance. If the contractor hid a defect fraudulently, longer periods can apply.
Deemed acceptance: don’t ignore the deadline
Silence can count as acceptance. Under § 640(2) BGB, the work is treated as accepted if the contractor, after finishing, set you a reasonable deadline for acceptance and you did not refuse within that deadline by naming at least one defect.
If you are a consumer, there is an extra safeguard: this only applies if the contractor, together with the request for acceptance, told you in text form (an email is enough) what happens if you don’t accept or refuse without naming defects. If that notice is missing, the deadline alone doesn’t make the work accepted.
Worked example: a painter finishes your apartment on Monday 2 November 2026 and emails you the same day: “The work is complete. Please accept it by Monday 16 November”, with a paragraph explaining that the work counts as accepted if you neither accept nor name a defect by then. On Thursday 12 November you notice paint on the window frames in two rooms. You email back that day, refusing acceptance and naming the defect, with photos. The work is not deemed accepted. Had you not replied by 16 November, it would have counted as accepted, and the price would have been due.
Reserve every defect you already know about
§ 640(3) BGB is the trap. If you accept work even though you know it has a defect, you keep the right to have it fixed, to fix it yourself at the contractor’s cost, and to withdraw or reduce the price only if you reserve your rights for that defect when you accept.
So a known defect that is not written down as reserved at acceptance can be lost, at least for those rights. The law ties the reservation to the acceptance itself, so don’t count on an email a few weeks later.
In practice: every defect you see on the day goes into the acceptance report, each one marked as reserved.
Worked example: a kitchen fitter installs your kitchen for €18,400. At the acceptance on 20 November 2026 you notice a 3 mm gap at the worktop joint and a cupboard door that doesn’t close. Both are minor, so you accept, and the report lists both as reserved defects with photos and a deadline of 4 December for the fix. The fitter estimates €300 to replace the worktop joint and €80 to adjust the door. Under § 641(3) you can hold back about €760, twice the €380, and pay the remaining €17,640.
If you refuse acceptance
If the defects are more than insignificant, you can refuse acceptance and name them. For building contracts, the contractor can then ask you to take part in a joint assessment of the condition of the work, signed by both of you, under § 650g BGB. If you don’t turn up to an agreed or reasonably set date, the contractor can do it alone, unless you couldn’t come for a reason you aren’t responsible for and told them promptly.
The record matters later: if the work has been handed over to you and an obvious defect is not listed in that assessment, it is presumed to have arisen afterwards and to be your responsibility. So take part, and make sure every visible defect is in it.
What to put in the acceptance report
The law doesn’t prescribe a form, but a report that holds the facts clearly saves arguments later:
- Who and what: names of everyone present, the contract or order it relates to, the address.
- Date and time of the acceptance.
- What was inspected: room by room, or part by part for larger work.
- Accepted or refused: in plain words, for the whole work or each part.
- Reserved defects: each one numbered, with location, description, size where it helps and photo numbers. Mark each as reserved.
- Disputed points: where the contractor doesn’t agree it is a defect, say so, with both views.
- Deadlines to fix each defect.
- Amount held back, if any, and for which defect.
- Remaining work, separate from defects: things not yet done at all.
- Handed over: keys, manuals, warranty cards, certificates, meter readings.
- Signatures, with a copy for each side.
A report written on the spot, with each photo next to the item it shows, leaves far less to argue about later. That is what our acceptance report is built for. You walk through the work and say what you see, in English, and AI writes each section, with each photo next to the defect it shows. Before you finish, AI lists what’s missing, such as a defect with no deadline, and you can change anything until you finish. The contractor can sign on your phone or later by email if they want to, and you get one sealed PDF with a verification code anyone can check.
Limits: when to get advice
This guide explains the general rules of the BGB. It is not legal advice. Your contract can change a lot: VOB/B terms, a property developer’s contract when you buy a new-build, or a contract for the common parts of a condominium each have their own points. Get advice from a lawyer who specializes in construction law, or from your local consumer advice center, before you refuse acceptance of a large job, hold back significant sums, or sign an acceptance report for a new home. For big projects, an independent building expert at the acceptance is worth the fee.
Questions people ask
- Can I refuse to accept work because of a small defect?
- No. Under § 640(1) BGB you can’t refuse acceptance because of an insignificant defect. Accept the work, list the defect in the acceptance report as reserved, and ask for it to be fixed by a date. For defects that are more than insignificant, you can refuse acceptance and name them.
- What happens if I just don’t reply to the contractor’s request?
- If the contractor set you a reasonable deadline after finishing and you neither accept nor refuse with at least one defect, the work can count as accepted (§ 640(2) BGB). If you are a consumer, that only applies if the contractor told you about this consequence in text form, such as an email, with the request.
- How long do I have to claim for defects after acceptance?
- For a building, and for planning or supervision work on a building, five years from acceptance. For work on a thing, such as repairing a car or a bike, two years. Other work falls under the general limitation period (§ 634a BGB). Your contract may say more, so check it.
- How much of the price can I hold back for a defect?
- If you are entitled to have a defect fixed, you can refuse to pay an appropriate part of the price once it is due. Under § 641(3) BGB that is usually twice the cost of fixing the defect. If the fix costs €400, you can hold back about €800 until it is done.
You talk. AI writes the report.
Acceptance report: walk through and say what you see. Then the PDF is sealed.
Sources
- Civil Code (BGB), § 640 Acceptance (gesetze-im-internet.de)
- German Civil Code, English translation (gesetze-im-internet.de)
- § 640 BGB, Acceptance (dejure.org)
- § 641 BGB, When payment is due (dejure.org)
- § 634a BGB, Limitation of claims for defects (dejure.org)
- Civil Code (BGB), § 650g Condition assessment when acceptance is refused (gesetze-im-internet.de)
- A defect must already exist at acceptance (BG BAU Bauportal)
- No defect rights before acceptance (Deutsches Handwerksblatt)
General information, not legal advice. Laws change: check the linked sources for your case.