Practical completion inspection: a checklist
Fiveover editorial team 8 min read
Practical completion is the point where the builder says the work is finished and hands it over. It is also the last moment you have the builder’s full attention, before the final payment changes hands. What you write down on the day, and how clearly, decides how easy it is to get the remaining items fixed.
This guide covers residential building work in New South Wales and Queensland. Victoria, WA, SA and the territories have their own laws and contracts, and the rules in your own contract always matter, so read it alongside this.
What practical completion means
In NSW, if your contract doesn’t say when the work is complete, completion happens at practical completion: the work is finished except for omissions or defects that don’t stop it being reasonably capable of being used for its intended purpose. That definition is in the Home Building Act 1989, and the NSW Government explains it the same way.
In Queensland, QBCC describes practical completion as the point where the building work is done and you can move in. The home must be suitable for occupation: it works as a normal home, has power and water, and is weatherproof. Some outstanding items, such as painting touch-ups, are allowed, but not major defects.
So “practically complete” is not the same as “perfect”. It means the leftovers are small enough to fix after you move in. Your job at the inspection is to find every one of them and get it in writing.
Why the date matters
Two things usually hang off practical completion:
- The final payment. QBCC says you don’t have to make the final contract payment until the work is done to the contract, plans and specifications and all legal requirements, with no defects or omissions, or only minor ones that won’t unreasonably affect occupation. In NSW, the MyHome Planner advises paying the final amount only once the builder has dealt with the issues from the pre-handover inspection and given you written notice that the work is complete.
- The warranty clocks. In NSW the statutory warranties run from completion of the work. In Queensland, QBCC’s time limits for complaints about non-structural defects run from completion too.
Worked example: a Queensland renovation contract for $210,000 has a final stage payment of $21,000 due at practical completion. The builder books the inspection for Thursday 12 November 2026. If you find a cracked shower screen, a missing towel rail and a door that won’t latch, those go on the defects document that day. You then pay what your contract says is due at practical completion, and the builder fixes the listed items as soon as practicable, with you giving reasonable access.
Queensland: the defects document
Under QBCC’s guidance, if you believe there are minor defects or minor omissions, the builder must give you a defects document listing the agreed and the non-agreed items, compiled with you at the handover inspection. On the QBCC New Home Construction Contract’s Form 6, the first part lists minor defects and omissions that both of you agree exist. The second part lists the extra items you say exist and the builder does not accept. Both sides sign and date it.
That second part matters. An item the builder disagrees with still belongs on the document, so there is a dated record that you raised it on the day.
QBCC’s time limits for complaints are worth knowing before you sign off. For a non-structural defect, a complaint must be lodged as soon as possible and no later than 12 months from completion, and, for a possible claim under the home warranty scheme on a defect that shows up in the first 6 months, within 7 months of completion. For a structural defect, within 12 months of noticing it (QBCC). Those limits are about complaints to QBCC. Your contract may also have its own notice periods.
NSW: the pre-handover inspection and the warranties
NSW has no statutory equivalent of Queensland’s defects document, but the advice is the same. The MyHome Planner recommends a final inspection with your builder before handover, taking your contract and inclusions list, listing anything missing, damaged or incomplete, and photographing every issue. It also suggests hiring a building consultant for the inspection.
Behind that sit the statutory warranties. Under the Home Building Act, the builder warrants among other things that the work is done with due care and skill, in line with the plans and specifications, and with proper materials. The warranty period is 6 years for a major defect and 2 years for any other defect, from completion of the work. If you find out about a breach in the last 6 months of either period, you have an extra 6 months to start proceedings. The warranties apply even if they are not written into the contract you signed (NSW Government).
A major defect is a serious defect in a major element of the building, such as the foundations, load-bearing walls, roof, waterproofing or fire safety systems. It comes from defective design, materials or workmanship, or a failure to comply with the National Construction Code, and it affects your ability to live in or use the building, or threatens collapse or destruction of all or part of it (MyHome Planner; the full definition is in the Act). Most items you find at practical completion are the 2-year kind: a sticking door, a chipped benchtop, patchy paint.
Many contracts also have a builder’s defects liability period, a set time after completion during which the builder comes back to fix items. MyHome Planner says it is usually 13 weeks for new homes. It sits on top of the statutory warranties and does not shorten them.
Worked example: a new home in Penrith reaches practical completion on 1 December 2026. A leaking window flashing that turns out to be a major defect can be pursued until 1 December 2032. A cracked tile is a 2-year item, until 1 December 2028. If you only notice the tile on 15 October 2028, inside the last 6 months, you have until 1 June 2029 to start proceedings.
How to run the walk-through
Book enough time. A three-bedroom house can take two hours or more to do properly. Go in daylight, with the power and water on, and bring:
- The contract, plans, specifications and the inclusions or colour selection list.
- Any variations you signed.
- A torch, a level or straight edge, a tape measure, painter’s tape to mark spots, and a charged phone.
- Someone with you, ideally an independent building inspector.
Go room by room in the same order, then outside. For each room, check ceilings, walls, floors, doors, windows, fittings and the items on your inclusions list. Turn on every tap, flush every toilet, run every appliance, open every window and cupboard.
Minor defects: write what you see
The defects list is only as useful as its wording. “Paint: poor” invites an argument. “Bedroom 2, north wall, paint drips 30 cm below cornice, photo 14” gets fixed. For each item, write:
- Where: room, wall or fixture, and a reference the builder can find again.
- What: the actual problem, with a size where it helps (“scratch 8 cm”, “gap 4 mm at skirting”).
- What it should be: the plan, specification or inclusion it fails (“tap model on selection sheet is X, installed Y”).
- Photo numbers next to the line they show, with a close-up and a wider shot for context.
- Agreed or disputed: whether the builder accepts it on the day.
- Due date for the fix, if you agree one.
Keep incomplete work separate from defects: a missing towel rail is an omission, a crooked one is a defect. Both go on the list.
Checklist of what to write down
- Date, start and end time, address, contract number.
- Names of everyone present, and who for the builder.
- Meter readings and the number of keys, remotes and fobs handed over.
- Each defect or omission, numbered, with location, description, photo numbers and agreed or disputed.
- Any certificates or documents handed over or still outstanding (for example, warranties and manuals).
- The builder’s promised dates for fixing items.
- Signatures, and a copy for each side.
A defects list written on the spot, with each photo next to the item it shows, leaves far less to argue about. That is what our practical completion defects list is built for. You walk through the house and say what you see, and AI writes each defect into the list with its photo next to it. Before you finish, AI lists what’s missing, such as a defect with no location, and you can change anything until you finish. The builder can sign on your phone or later by email if they want to, and you get one sealed PDF with a verification code anyone can check. In Queensland it doesn’t replace the defects document in your QBCC contract: fill that in and attach the PDF.
If the builder disagrees
Disagreement at handover is normal. Handle it in writing:
- Put it on the list anyway, marked as disputed. In Queensland, that is the non-agreed part of the defects document.
- Point to the source: the plan, specification, inclusion or standard you rely on, and the photo.
- Follow up by email the same day with the full list attached, asking the builder to confirm the agreed items and the dates.
- Get an independent view on disputed items, from a building inspector.
- Use the dispute process if it stalls. In NSW, Fair Trading runs a free complaint service for residential building work and expects you to try to sort it out with the builder first. If an inspector finds the builder responsible, they can issue a rectification order. In Queensland, QBCC handles complaints about defective work, within the time limits above.
Don’t withhold more than your contract allows. Holding back the final payment when the contract says it is due can put you in breach, even if you are right about the defects. If the amounts are large, get advice before you decide.
Limits: when to get advice
This guide explains the general rules in NSW and Queensland. It is not legal advice. Contracts differ (QBCC’s own contracts, industry association contracts and builders’ own forms each have their own completion clauses), and your contract’s notice periods and payment terms can matter as much as the law. Get independent advice before you refuse a practical completion notice, withhold money, or sign anything that says the work is accepted without defects. A building inspector is worth booking for the inspection itself, and a lawyer is worth calling if there is a structural problem or the builder stops responding.
Questions people ask
- Do I have to pay the final payment if there are defects?
- In Queensland, QBCC says you don’t have to make the final payment until the work is done to the contract, plans and legal requirements, with no defects or only minor ones that won’t unreasonably affect occupation. In NSW, the government’s advice is to pay only once the builder has dealt with the pre-handover issues and given you written notice that the work is complete. Check what your contract says.
- What is a defects document in Queensland?
- It is the list of minor defects and minor omissions at practical completion. Under QBCC contracts the builder compiles it with you at the handover inspection and you both sign it. One part lists the items you both agree on, the other the items you say exist and the builder does not accept.
- How long is the statutory warranty in NSW?
- Under the Home Building Act 1989, 6 years for a major defect and 2 years for any other defect, both from completion of the work. If you find the problem in the last 6 months of either period, you get an extra 6 months to start proceedings.
- What if the builder says an item isn’t a defect?
- Write it on the list anyway, marked as disputed, with a photo and the clause or plan reference you rely on. In Queensland that is what the non-agreed part of the defects document is for. If you still can’t agree, NSW Fair Trading and QBCC both have dispute processes, with time limits.
You talk. AI writes the report.
Practical completion and defects list: walk through and say what you see. Then the PDF is sealed.
Sources
- Practical completion inspection (QBCC)
- QBCC New Home Construction Contract, Form 6: Defects Document (QBCC)
- Help with defective work (QBCC)
- Home Building Act 1989 (NSW Legislation)
- Contracts for residential building work (NSW Government)
- Post-build (MyHome Planner, NSW Planning Portal)
- Defects and warranties (MyHome Planner, NSW Planning Portal)
- Building defect complaints (NSW Fair Trading)
- Resolving building disputes with your builder or tradesperson (NSW Government)
General information, not legal advice. Laws change: check the linked sources for your case.